The Landings, Te Aroha (Stage 2 and 3)

Total Value: $5.6 million

ECS Services: Financial Institution Services

Project Duration: Stage 2 complete (August 2016 to April 2017). Stage 3 ongoing

Client: Onward Development Group

Main Contractor: The works are being administered and managed by Onward Development Group together with GeoMetrix Ltd

Architect: GeoMetrix Ltd

Structural: TBC

Service: TBC

Others: Tonkin & Taylor (geotechnical engineer)

Development at 25-31 Terminus Street comprises 21 residential units (stages 2 and 3) made up of 11, one or two unit blocks. Construction comprises timber wall and roof framing. The external envelopes are made up of clay brick cladding, double glazed aluminium joinery and metal tile roofing. Internal partitions are timber-framed with inter-tenancy firewalls between units. All units comprise two to three bedrooms and an attached garage. Externally, a concrete driveway is provided to each garage from the cul-de-sac roading off Terminus Street.

ECS involvement began with stage 2 of the development which is now complete. Stage 3 is currently in progress and is programmed for completion in July 2017.